Project Specifications


Client
Brookfield District Energy

Value
$8.8 million

Location
Sydney, New South Wales

Completion
September 2016

Extension of chilled water piping from under Broadway into the UTS building.

PROJECT DESCRIPTION

lol英雄联盟积分新版v3.5(lol英雄联盟季节今日可靠) Construction was asked to install and commission an energy transfer station in UTS to link the Central Park CTP to the UTS Central Energy Plant.

Directional drilling was undertaken to allow pipe installation from Jones Street through to UTS building 02. We also installed and pressure-tested the HDPE pipe. This pipe transports chilled water to the building and used for cooling.

OVERCOMING CHALLENGES

We were working in a live environment with students and the general public. Safety was of the utmost importance as was reducing noise levels so as not to interrupt student exams.

INNOVATIONS

Our client had the benefit of our knowledge of the existing Central Park plant and the experience in implementing the energy transfer systems. This resulted in a rapid design development phase.

Project Contact

Steve Taylor
Managing Director (Founding Shareholder)

Steve is a founding shareholder of lol英雄联盟积分新版v3.5(lol英雄联盟季节今日可靠) Construction. Equipped with a carpentry trade background and extensive experience with design and construct projects across all sectors of the building industry, Steve has been a driving force behind the company’s growth and success. With the appointment of a Chairman and CEO, Steve now focuses on the continual development of a successful and sustainable strategy for the business. He also plays a key role in providing leadership for the overall development of the company through strategic marketing, client relationships and procurement. Steve is based in Sydney where he has the overall management in NSW.

王者荣耀电竞 lpl外围手机版 亿博电竞最新版外围永久 lpl电竞官方观看正规 ig电子竞技(新疆)结果视频 2022lpl(长沙)抽注下载6.9.7
`